Man-Days-Hours Work Equivalence Problems
Quantitative Aptitude › Time and Work, Pipes and Cisterns · Topic 9.7
In man-days-hours problems, the total work equals the number of men times the days times the hours worked per day. For the same job, men × days × hours is constant, and the equation M1 D1 H1 / W1 = M2 D2 H2 / W2 handles changes in all three.
5 min read · Quantitative Aptitude · Time and Work, Pipes and Cisterns
Quick Answer
In man-days-hours problems, the total work equals the number of men times the days times the hours worked per day. For the same job, men × days × hours is constant, and the equation M1 D1 H1 / W1 = M2 D2 H2 / W2 handles changes in all three.
At a Glance
- Total work Men × Days × Hours
- Equation M1 D1 H1 / W1 = M2 D2 H2 / W2
- Same work M1 D1 H1 = M2 D2 H2
- More men Fewer days
- More hours per day Fewer days
- Unit Man-hours
Where Does It Fit?
This topic generalises Work and Efficiency Relationship (Inverse Proportion) by adding hours per day. It is used in Work Left/Completed When People Join or Leave Midway and Work Problems Involving Men, Women and Children Working Together at Different Rates.
What Is the Man-Days-Hours Equation?
In short: the amount of work is proportional to men, days and hours, so the same job satisfies a constant product.
Work equation
- M1 × D1 × H1 / W1 = M2 × D2 × H2 / W2
- If the work is the same, M1 D1 H1 = M2 D2 H2.
- The unit of work is the man-hour.
12 men working 8 hours a day finish a job in 15 days, so the work is 12 × 8 × 15 = 1440 man-hours. With 18 men working 10 hours a day, the days needed are 1440 / (18 × 10) = 8.
How Does Changing the Work Amount Affect the Result?
| Quantity | Relation | Example |
|---|---|---|
| More work | More man-hours needed | Doubling the road length doubles the man-hours |
| More men | Fewer days | 18 men instead of 12 men |
| More hours | Fewer days | 10 hours instead of 8 hours |
If 10 men build 150 m of road in 12 days working 6 hours a day, the work is 720 man-hours per 150 m. For 300 m in 10 days of 9 hours, the man-hours are 1440 and the men needed are 1440 / 90 = 16.
How Do You Handle Different Efficiencies?
- Convert to equal units: if 3 men equal 5 women in work, convert all workers to one type before using the equation.
- Different tasks: divide by the work amount W to get man-hours per unit.
- Chairs example: 40 men make 600 chairs in 12 days, so each chair takes 0.8 man-days. For 450 chairs, 360 man-days are needed, and 30 men take 12 days.
Solved Examples
Example 1
Question: 12 men working 8 hours a day finish a job in 15 days. How many days will 18 men working 10 hours a day need?
- Work = 12 × 8 × 15 = 1440 man-hours.
- Daily man-hours of 18 men = 180.
- Days = 1440 / 180 = 8.
Answer: 8 days
Example 2
Question: 10 men build 150 m of road in 12 days working 6 hours a day. How many men are needed for 300 m in 10 days working 9 hours a day?
- Man-hours for 150 m = 10 × 12 × 6 = 720.
- Man-hours for 300 m = 1440.
- Man-hours per man = 10 × 9 = 90.
- Men = 1440 / 90 = 16.
Answer: 16 men
Example 3
Question: 20 men working 8 hours a day complete a job in 15 days. How many hours a day must 25 men work to finish in 12 days?
- Work = 20 × 15 × 8 = 2400 man-hours.
- Man-days of 25 men = 25 × 12 = 300.
- Hours = 2400 / 300 = 8.
Answer: 8 hours a day
Example 4
Question: 15 men working 6 hours a day take 20 days to finish a work. How many days will 10 men working 9 hours a day take?
- Work = 15 × 6 × 20 = 1800 man-hours.
- Daily man-hours = 10 × 9 = 90.
- Days = 1800 / 90 = 20.
Answer: 20 days
Example 5
Question: 40 men make 600 chairs in 12 days. How many days will 30 men take to make 450 chairs?
- Man-days per chair = 40 × 12 / 600 = 0.8.
- For 450 chairs = 360 man-days.
- Days for 30 men = 360 / 30 = 12.
Answer: 12 days
Shortcuts and Tricks
- Compute the total man-hours first, then divide by the new daily man-hours.
- Always include W when the amount of work changes.
- Convert women, children or machines into one equivalent type first.
- Keep units consistent, such as hours per day.
- Check direction: more resources, fewer days.
Common Mistakes
- Ignoring the hours per day.
- Leaving out the work amount W when the job changes.
- Treating days and hours as the same unit.
- Forgetting to convert unequal workers into equivalent units.
- Reversing the proportions between men and days.
Practice Questions
- 12 men working 8 hours a day finish a job in 15 days. How many days for 18 men at 10 hours a day?
- 10 men, 150 m, 12 days, 6 hours a day. How many men for 300 m in 10 days at 9 hours a day?
- 20 men, 15 days, 8 hours a day. For 25 men in 12 days, how many hours a day?
- 15 men, 6 hours a day, 20 days. How many days for 10 men at 9 hours a day?
- 40 men make 600 chairs in 12 days. How many days for 30 men and 450 chairs?
Answers: 1) 8 days; 2) 16; 3) 8; 4) 20 days; 5) 12 days.
Why Is This Topic Important?
- Complete model It handles men, days, hours and quantity together.
- Exam use Common in tougher time and work questions.
- Method It reinforces constant-product thinking.
- Link It is a base for Work Problems Involving Men, Women and Children Working Together at Different Rates.
What Comes Next?
The next topic is Work Completed in a Fractional/Part Day Problems, which deals with work finished in fractions of a day.
Key Terms and Formulas
- Man-hour One man working for one hour
- Man-day One man working for one day
- Work amount Quantity of work such as metres or chairs
- Daily hours Hours worked per day
- Equivalent worker A worker counted as a standard unit
- Constant product Fixed total for the same job
Related Topics
- Pipes Working Together, Alternately or with One Acting as an Outlet
- Work Completed in a Fractional/Part Day Problems
- Work and Efficiency Relationship (Inverse Proportion)
- Combined Work by Multiple Persons or Groups
Exam Corner
Points to Remember
- Total work = men × days × hours.
- M1 D1 H1 / W1 = M2 D2 H2 / W2.
- More men or hours means fewer days.
- More work means more man-hours.
- Convert unequal workers to one type.
Do Not Confuse With
- Man-days vs man-hours Man-hours also include hours per day.
- Days vs hours per day Both reduce when resources rise.
- Work amount vs total work Work amount is the output; man-hours are the effort.
- Same job vs different job Include W when the job changes.
Memory Hook
Men times days times hours is the effort; match effort to work.
GS Relevance
Frequently Asked Questions
What is the man-days-hours formula?
The man-days-hours formula states that the work done is proportional to men multiplied by days multiplied by hours per day. For two situations, M1 times D1 times H1 divided by W1 equals M2 times D2 times H2 divided by W2, where W is the amount of work, so for the same job the product is constant.
How do you find the days when men and hours change?
To find the days when men and hours change, first compute the total man-hours of the original job as men times days times hours. Then divide that total by the new number of men multiplied by the new hours per day. For 12 men, 8 hours, 15 days, 18 men at 10 hours need 8 days.
How do you include a change in the amount of work?
A change in the amount of work is included by dividing each side of the equation by its work quantity W. If the work doubles, the man-hours needed double. For 150 m taking 720 man-hours, 300 m needs 1440 man-hours, so the number of men or days must double.
How do you handle workers with different efficiencies?
Workers with different efficiencies are first converted into one type of equivalent worker. If 3 men equal 5 women in work, replace the women by the equivalent number of men, then apply the man-days-hours equation to the converted total with the same days and hours.
Why does more hours per day reduce the days needed?
More hours per day reduce the days needed because each day delivers more man-hours of work. For the same total work, the product of men, days and hours is fixed, so when hours per day rise from 8 to 10 the days fall in the inverse proportion.
PYQ Practice — Statement Analysis
1 For the same job, men × days × hours per day is constant.
The total man-hours of work is fixed.
2 If men are increased, the days needed for the same job increase.
More men reduce the days needed.
3 12 men working 8 hours a day for 15 days do 1440 man-hours of work.
12 × 8 × 15 = 1440.
4 Doubling the work with the same men and hours doubles the days needed.
The man-hours required double.
Related Topics
Browse the full Quantitative Aptitude index