Work and Efficiency Relationship (Inverse Proportion)
Quantitative Aptitude › Time and Work, Pipes and Cisterns · Topic 9.1
Work and efficiency are linked by inverse proportion: the more efficient a worker, the fewer days needed for the same job. If a worker finishes a job in d days, the work done in one day is 1/d of the job.
6 min read · Quantitative Aptitude · Time and Work, Pipes and Cisterns
Quick Answer
Work and efficiency are linked by inverse proportion: the more efficient a worker, the fewer days needed for the same job. If a worker finishes a job in d days, the work done in one day is 1/d of the job.
At a Glance
- One day’s work 1 / Days taken
- Work Efficiency × Time
- Efficiency and time Inversely proportional
- LCM method Take total work as the LCM of the days
- Men and days M1 × D1 = M2 × D2
- Efficiency ratio Inverse of the ratio of days
Where Does It Fit?
This is the first topic of the Time and Work macro. It leads into Combined Work by Multiple Persons or Groups, Work and Wages Distribution Problems and Work Left/Completed When People Join or Leave Midway, and the same idea of rate drives Pipes and Cisterns – Filling and Emptying Problems on pipes and cisterns.
What Is the Relationship Between Work, Efficiency and Time?
In short: work done equals efficiency multiplied by time. For a fixed job, a worker who is twice as efficient takes half the time.
Basic relations
- Work = Efficiency × Time
- If a worker takes d days, one day’s work = 1/d
- If A takes a days and B takes b days, efficiency ratio A : B = b : a
- For a fixed job, M1 × D1 = M2 × D2
If A can finish a job in 12 days and B in 18 days, A’s efficiency to B’s is 18 : 12 = 3 : 2, so A does 3 parts of work for every 2 parts done by B.
How Does the LCM Method Work?
In short: assume the total work is the LCM of the days taken, so that each worker’s daily work becomes a whole number.
| Worker | Days | Total work (LCM = 36 units) | Units per day |
|---|---|---|---|
| A | 12 | 36 | 36 / 12 = 3 |
| B | 18 | 36 | 36 / 18 = 2 |
| A + B | ? | 36 | 3 + 2 = 5, so 36 / 5 = 7.2 days |
The LCM method avoids fractions, and the result does not depend on the actual units of work. LCM itself is explained in Lowest Common Multiple (LCM) by Division and Prime Factorization Method.
How Do Men, Days and Efficiency Combine?
- Same efficiency: men × days is constant. 12 men finish a job in 15 days, so 18 men take 12 × 15 / 18 = 10 days.
- Different efficiency: if A is 50 per cent more efficient than B and B takes 30 days, A takes 30 / 1.5 = 20 days.
- Twice as fast: if A is twice as fast as B and together they take 12 days, then A alone takes 18 days and B alone 36 days.
Solved Examples
Example 1
Question: A can finish a job in 12 days and B in 18 days. Find the ratio of their efficiencies.
- Efficiency is inversely proportional to days.
- A : B = 18 : 12.
- Simplify 18 : 12 to 3 : 2.
Answer: 3 : 2
Example 2
Question: A is 50 per cent more efficient than B, and B takes 30 days. How long does A take?
- A’s efficiency = 1.5 × B’s efficiency.
- Time of A = 30 / 1.5 = 20.
Answer: 20 days
Example 3
Question: 12 men can finish a work in 15 days. How many days will 18 men take?
- Total work = 12 × 15 = 180 man-days.
- Days for 18 men = 180 / 18 = 10.
Answer: 10 days
Example 4
Question: A takes 12 days and B takes 18 days. Using the LCM method, find the daily work of each.
- LCM of 12 and 18 is 36 units of work.
- A’s daily work = 36 / 12 = 3 units.
- B’s daily work = 36 / 18 = 2 units.
Answer: A: 3 units per day; B: 2 units per day
Example 5
Question: A is twice as fast as B. Together they finish a job in 12 days. How long would A alone take?
- Let B do 1 part per day, so A does 2 parts per day and together 3 parts.
- Total work = 3 × 12 = 36 parts.
- A alone = 36 / 2 = 18 days.
Answer: 18 days
Shortcuts and Tricks
- Use the LCM method to turn fractions into whole numbers.
- For same-efficiency workers, keep men × days constant.
- Convert a percentage efficiency gap into a ratio, such as 150 : 100 = 3 : 2.
- If one worker is k times as fast, he takes 1/k of the time.
- Check your answer by recomputing total work from daily rates.
Common Mistakes
- Treating efficiency as directly proportional to days.
- Adding days instead of daily work rates.
- Forgetting to convert percentage efficiency into a ratio.
- Using different units of work for different workers.
- Assuming more men always cut time in proportion when efficiencies differ.
Practice Questions
- A takes 15 days and B takes 10 days. Find the ratio of efficiencies A : B.
- 8 men finish a job in 15 days. How many days will 12 men take?
- A is 25 per cent more efficient than B, and B takes 20 days. How long does A take?
- A takes 6 days and B takes 9 days. Find the ratio of daily work A : B.
- 20 workers finish a task in 18 days. How many days will 15 workers take?
Answers: 1) 2 : 3; 2) 10 days; 3) 16 days; 4) 3 : 2; 5) 24 days.
Why Is This Topic Important?
- Foundation Every work and pipe problem uses efficiency.
- Speed The LCM method removes fractions.
- Exam use Direct efficiency questions appear in most papers.
- Link The same logic drives Pipes and Cisterns – Filling and Emptying Problems and Speed, Distance and Time Basic Relationship and Unit Conversion (km/h to m/s).
What Comes Next?
The next topic is Combined Work by Multiple Persons or Groups, where several workers or groups work together on the same job.
Key Terms and Formulas
- Efficiency Work done per unit time
- One day’s work Fraction of the job done in a day
- LCM method Take total work as the LCM of the days
- Man-days Men multiplied by days
- Inverse proportion One rises as the other falls
- Total work The whole job, taken as 1 or as an LCM
Related Topics
- Combined Work by Multiple Persons or Groups
- Work and Wages Distribution Problems
- Work Left/Completed When People Join or Leave Midway
- Pipes and Cisterns – Filling and Emptying Problems
Exam Corner
Points to Remember
- One day’s work = 1 / days taken.
- Work = efficiency × time.
- Efficiency and time are inversely proportional.
- Use LCM of days as the total work.
- Men × days stays constant for the same job and efficiency.
Do Not Confuse With
- Efficiency vs days More efficient means fewer days.
- Total work vs daily work Total work is the whole job; daily work is the part done in a day.
- Men-days vs days Man-days count workers as well as time.
- Ratio of days vs ratio of efficiency They are inverse of each other.
Memory Hook
Faster worker, fewer days: efficiency and time are opposites.
GS Relevance
Frequently Asked Questions
What is the relationship between work and efficiency?
Work done equals efficiency multiplied by time, and efficiency is inversely proportional to the time taken for a fixed job. A worker who finishes a job in 12 days does one twelfth of the job in a day, so a more efficient worker needs fewer days to complete the same work.
How does the LCM method work in time and work?
The LCM method takes the total work as the lowest common multiple of the days taken by the workers. Each worker's daily work then becomes a whole number, found by dividing the total work by days. For 12 and 18 days, total work is 36 units, giving daily work of 3 and 2 units.
How do you find the ratio of efficiencies from days?
The ratio of efficiencies is the inverse of the ratio of days taken. If A takes 12 days and B takes 18 days, then A's efficiency to B's efficiency is 18 to 12, which simplifies to 3 to 2, so A works one and a half times as fast as B.
How do men and days relate in a work problem?
For the same job and equal efficiency, the product of men and days is constant. If 12 men finish a job in 15 days, the work is 180 man-days, so 18 men will finish it in 180 divided by 18, which is 10 days.
If A is 50 per cent more efficient than B, how long does A take?
If A is 50 per cent more efficient than B, A works at 1.5 times B's rate and takes B's time divided by 1.5. For B taking 30 days, A takes 30 divided by 1.5, which is 20 days, because the time taken is inversely proportional to efficiency.
PYQ Practice — Statement Analysis
1 If a worker finishes a job in d days, one day's work is 1/d of the job.
The job is the sum of d equal daily parts.
2 If A takes 12 days and B takes 18 days, the efficiency ratio A : B is 2 : 3.
It is 18 : 12 = 3 : 2, the inverse of the days ratio.
3 For the same job and efficiency, men multiplied by days is constant.
Total man-days is the fixed amount of work.
4 12 men finishing a job in 15 days means 18 men finish it in 10 days.
12 × 15 / 18 = 10.