79 RAS Prelims MCQs on energy infrastructure in Rajasthan cover renewable energy, power distribution and the financial health of DISCOMs. The Solar Energy Policy 2019, wind parks, the Green Energy Corridor, UDAY, RDSS, smart meters, AT&C losses and green hydrogen are asked as facts, causes and effects.

Practice questions based on the RPSC RAS Prelims syllabus. They follow the exam pattern but are not past-paper questions.

Clear filters

Showing 41–50 of 79 questions

RAS Prelims Rajasthan Economy · Energy Infrastructure in Rajasthan
Q41. Consider the following statements regarding the functions of the Rajasthan Renewable Energy Corporation (RREC):
I. It acts as the State Nodal Agency for the Ministry of New and Renewable Energy (MNRE).
II. It is responsible for regulating the power tariffs of thermal power plants.
III. It promotes energy conservation programs under the Bureau of Energy Efficiency.
IV. It facilitates the single-window clearance system for renewable energy developers.
Which of the above statement(s) is/are correct?
RAS Prelims Rajasthan Economy · Energy Infrastructure in Rajasthan
Q42. Which of the following is a correct statement regarding RREC?
RAS Prelims Rajasthan Economy · Energy Infrastructure in Rajasthan
Q43. Where is the headquarters of the Rajasthan Renewable Energy Corporation Limited (RRECL) located?
RAS Prelims Rajasthan Economy · Energy Infrastructure in Rajasthan
Q44. Match List-I with List-II and select the correct answer:
DISCOMsDistricts under their jurisdiction
A. Jaipur Vidyut Vitran Nigam Ltd (JVVNL)i. Bikaner, Barmer, Jaisalmer
B. Ajmer Vidyut Vitran Nigam Ltd (AVVNL)ii. Bhilwara, Nagaur, Sikar
C. Jodhpur Vidyut Vitran Nigam Ltd (JdVVNL)iii. Alwar, Bharatpur, Dausa
D. Power distribution in Kota city (Franchisee)iv. CESC Limited
RAS Prelims Rajasthan Economy · Energy Infrastructure in Rajasthan
Q45. The unbundling of the former Rajasthan State Electricity Board (RSEB) in the year 2000 was primarily driven by the concept of:
RAS Prelims Rajasthan Economy · Energy Infrastructure in Rajasthan
Q46. Consider the following statements regarding the power distribution companies (DISCOMs) in Rajasthan:
I. JdVVNL covers the maximum number of districts among the three DISCOMs.
II. JdVVNL operates in the highly desert-dominated western districts, leading to high infrastructure costs.
III. The DISCOMs purchase power primarily through Rajasthan Urja Vikas Nigam Limited (RUVNL).
IV. The distribution network in Rajasthan faces challenges like long transmission lines and sparse population density.
V. DISCOMs in Rajasthan have consistently registered massive net profits over the last decade.
Which of the above statement(s) is/are incorrect?
RAS Prelims Rajasthan Economy · Energy Infrastructure in Rajasthan
Q47. Which of the following districts does NOT fall under the jurisdiction of the Ajmer Vidyut Vitran Nigam Limited (AVVNL)?
RAS Prelims Rajasthan Economy · Energy Infrastructure in Rajasthan
Q48. Given below are two statements regarding power transmission:
Statement I: Rajasthan Rajya Vidyut Prasaran Nigam Limited (RVPNL) operates the high-voltage transmission network (132 kV and above) in the state.
Statement II: RVPNL directly supplies electricity to domestic consumers in rural areas.
Which of the above statement(s) is/are correct?
RAS Prelims Rajasthan Economy · Energy Infrastructure in Rajasthan
Q49. The "Green Energy Corridor" project being implemented in Rajasthan by RVPNL is primarily designed for:
RAS Prelims Rajasthan Economy · Energy Infrastructure in Rajasthan
Q50. Consider the following statements regarding power transmission in Rajasthan:
I. The State Load Despatch Centre (SLDC) is managed by RVPNL to ensure integrated operation of the power system.
II. Rajasthan shares inter-state transmission lines with Gujarat, Madhya Pradesh, and Punjab.
III. Transmission losses in the RVPNL network are higher than the distribution losses in the DISCOM network.
Which of the above statement(s) is/are correct?

Answer key for these questions

QCorrect answer
41(c) I, III and IV
42(b) It monitors renewable projects and formulates related state policies.
43(d) Jaipur
44(a) A-iii, B-ii, C-i, D-iv
45(c) Separating generation, transmission, and distribution to improve operational efficiency.
46(a) I and V only
47(d) Jodhpur
48(c) Statement I is correct but Statement II is incorrect.
49(d) Evacuating renewable energy (solar and wind) to the national grid.
50(a) I and II only

Key facts from Energy Infrastructure in Rajasthan

  • Under the Rajasthan Solar Energy Policy 2019, the 30 GW target gave 24 GW to utility-scale solar parks.
  • Soda Bandhan is a wind energy park in Jaisalmer.
  • The Green Energy Corridor of RVPNL evacuates solar and wind power to the national grid.
  • AT&C losses means Aggregate Technical and Commercial losses; theft, unmetered connections and poor collection cause them.
  • UDAY brought a debt takeover for DISCOMs; RDSS funds smart metering and infrastructure upgrades; PM-KUSUM solarises agricultural pumps and Saubhagya electrified households.
  • Pre-paid smart meters give upfront revenue collection; Rajasthan can be a green hydrogen hub because of its cheap renewable power.

Frequently asked questions

How many RAS Prelims practice MCQs are there on Energy Infrastructure in Rajasthan?

This page has 79 practice MCQs on Energy Infrastructure in Rajasthan (Rajasthan Economy). Each has the correct answer, and most have an explanation.

What does AT&C loss mean?

Aggregate Technical and Commercial losses, which combine the energy lost in transmission and distribution with the revenue lost through theft, billing errors and poor collection. It is the main measure of a DISCOM’s efficiency.

Which scheme is used to install smart meters in Rajasthan?

The Revamped Distribution Sector Scheme (RDSS). It supports smart metering and distribution upgrades to reduce AT&C losses, and pre-paid smart meters help DISCOMs get their revenue upfront, which improves their cash flow.

What is the solar capacity target of the 2019 policy?

30 GW, of which 24 GW is allotted to utility or grid-scale solar parks. The rest is meant for rooftop, decentralised projects and solar pumps, which together are a much smaller part of the target.