Work and Wages Distribution Problems
Quantitative Aptitude › Time and Work, Pipes and Cisterns · Topic 9.3
In work and wages problems, the total wage is shared in proportion to the work each person actually does. Work done equals efficiency multiplied by days worked.
5 min read · Quantitative Aptitude · Time and Work, Pipes and Cisterns
Quick Answer
In work and wages problems, the total wage is shared in proportion to the work each person actually does. Work done equals efficiency multiplied by days worked.
At a Glance
- Rule Wages are proportional to work done
- Work done Efficiency × Days worked
- Equal efficiency Wages follow the ratio of days
- Same days Wages follow the ratio of efficiency
- Efficiency ratio Inverse of days to finish alone
- Share Total wage × ratio part / sum of parts
Where Does It Fit?
This topic follows Combined Work by Multiple Persons or Groups and prepares for Work Sharing and Wage Distribution Based on Efficiency Ratio. It uses efficiency from Work and Efficiency Relationship (Inverse Proportion).
How Are Wages Divided Among Workers?
In short: each worker’s share of the wage equals the share of the work that worker did.
Wage-sharing rule
- Share of A = (Work done by A / Total work) × Total wage
- If all work for the same time, wages follow the ratio of efficiencies.
- If efficiencies are equal, wages follow the ratio of days worked.
A can finish a job in 12 days and B in 6 days. Their efficiency ratio is 1/12 : 1/6 = 1 : 2, so from Rs 1800 A gets Rs 600 and B gets Rs 1200.
How Do You Handle Three Workers?
| Worker | Days alone | Efficiency | Share of Rs 6000 |
|---|---|---|---|
| A | 15 | 1/15 = 2/30 | 2/6 = Rs 2000 |
| B | 10 | 1/10 = 3/30 | 3/6 = Rs 3000 |
| C | 30 | 1/30 = 1/30 | 1/6 = Rs 1000 |
The efficiency ratio is 2 : 3 : 1, and the parts sum to 6. This works only when all three work for the same number of days, as they do when they work together from start to finish.
What If Workers Put in Different Numbers of Days?
- Equal efficiency: A works 10 days and B works 6 days at the same rate, so from Rs 1600 A gets 10/16 = Rs 1000 and B gets 6/16 = Rs 600.
- Different efficiency and days: multiply efficiency by days for each worker, then split the wage in the ratio of the products.
- Based on days alone: for A taking 20 days and B 30 days on a Rs 3000 job together, the ratio is 1/20 : 1/30 = 3 : 2, giving Rs 1800 and Rs 1200.
Solved Examples
Example 1
Question: A can do a job in 12 days and B in 6 days. They work together and earn Rs 1800. Find each share.
- Efficiency A : B = 1/12 : 1/6 = 1 : 2.
- A’s share = 1/3 of 1800 = 600.
- B’s share = 2/3 of 1800 = 1200.
Answer: A: Rs 600; B: Rs 1200
Example 2
Question: A, B and C can finish a job in 15, 10 and 30 days. Working together they earn Rs 6000. Find each share.
- Efficiencies 1/15 : 1/10 : 1/30 = 2 : 3 : 1.
- Shares = 2/6, 3/6 and 1/6 of 6000.
- A = 2000, B = 3000, C = 1000.
Answer: A: Rs 2000; B: Rs 3000; C: Rs 1000
Example 3
Question: A and B have equal efficiency. A works for 10 days and B for 6 days. They are paid Rs 1600 in all. Find each share.
- Wages follow days worked: 10 : 6.
- A = 10/16 × 1600 = 1000.
- B = 6/16 × 1600 = 600.
Answer: A: Rs 1000; B: Rs 600
Example 4
Question: A can do a job in 20 days and B in 30 days. Together they are paid Rs 3000. Find each share.
- Efficiency A : B = 1/20 : 1/30 = 3 : 2.
- A = 3/5 × 3000 = 1800.
- B = 2/5 × 3000 = 1200.
Answer: A: Rs 1800; B: Rs 1200
Example 5
Question: A is twice as efficient as B. They work together for 6 days and are paid Rs 900. How much does A earn?
- Efficiency ratio A : B = 2 : 1.
- A’s share = 2/3 of 900.
- 2/3 × 900 = 600.
Answer: Rs 600
Shortcuts and Tricks
- Use the ratio of efficiencies, which is the inverse ratio of days to finish alone.
- Convert ratios to whole numbers using the LCM method.
- Multiply efficiency by days when both differ.
- Share = ratio part / total parts × total wage.
- Check that the shares add up to the total wage.
Common Mistakes
- Sharing wages in the ratio of days to finish alone instead of its inverse.
- Ignoring that workers worked different numbers of days.
- Forgetting to add the ratio parts to find the denominator.
- Giving the same wage to workers of unequal efficiency.
- Using wages per day when total wages are asked.
Practice Questions
- A takes 12 days and B takes 6 days. They earn Rs 1800 together. Find A’s share.
- A takes 15 days, B 10 days and C 30 days. They earn Rs 6000. Find B’s share.
- A and B have equal efficiency. A works 10 days and B 6 days for Rs 1600. Find B’s share.
- A takes 20 days and B takes 30 days. They earn Rs 3000 together. Find B’s share.
- A is three times as efficient as B. They earn Rs 2000 together. Find B’s share.
Answers: 1) Rs 600; 2) Rs 3000; 3) Rs 600; 4) Rs 1200; 5) Rs 500.
Why Is This Topic Important?
- Realistic Wage sharing is a common practical problem.
- Method It reuses efficiency and ratio skills.
- Frequency Questions on wages appear in most papers.
- Link It prepares for Work Sharing and Wage Distribution Based on Efficiency Ratio.
What Comes Next?
The next topic is Work Left/Completed When People Join or Leave Midway, where workers join or leave in the middle of a job.
Key Terms and Formulas
- Wage Payment for the work done
- Efficiency Rate of work per day
- Share Part of the wage for one worker
- Ratio Comparison of two or more quantities
- Work done Efficiency multiplied by days worked
- Total wage Sum paid to all workers
Related Topics
- Combined Work by Multiple Persons or Groups
- Work Left/Completed When People Join or Leave Midway
- Work and Efficiency Relationship (Inverse Proportion)
- Pipes and Cisterns – Filling and Emptying Problems
Exam Corner
Points to Remember
- Wages are proportional to the work done.
- Work done = efficiency × days.
- Efficiency ratio is the inverse of the days ratio.
- Equal days: share by efficiency; equal efficiency: share by days.
- Shares must add up to the total wage.
Do Not Confuse With
- Days ratio vs efficiency ratio They are inverse of each other.
- Work done vs days worked Work done also includes efficiency.
- Share vs wage per day Share is the total received.
- Equal pay vs fair pay Fair pay follows the work done.
Memory Hook
Pay follows work: efficiency times days.
GS Relevance
Frequently Asked Questions
How are wages divided in time and work problems?
Wages in time and work problems are divided in proportion to the work done by each person. If workers work for the same time, the wage is shared in the ratio of their efficiencies. If efficiencies are equal, it is shared in the ratio of days worked, and otherwise efficiency is multiplied by days.
How do you find the wage ratio from days taken?
The wage ratio equals the ratio of efficiencies, which is the inverse of the ratio of the days each person takes alone. If A takes 12 days and B takes 6 days, the efficiency ratio is 1/12 to 1/6, which is 1 to 2, so B earns twice as much as A.
What if workers put in different numbers of days?
When workers put in different numbers of days, wages follow the product of efficiency and days for each worker. If efficiencies are equal, wages simply follow the days worked. For 10 days and 6 days on Rs 1600, shares are Rs 1000 and Rs 600.
How do you share a wage among three workers?
A wage among three workers is shared by finding the ratio of their efficiencies and splitting the total in that ratio. For workers taking 15, 10 and 30 days, efficiencies are in the ratio 2 to 3 to 1, so Rs 6000 is divided as Rs 2000, Rs 3000 and Rs 1000.
Why should wages follow work and not days alone?
Wages should follow the work done and not days alone because a faster worker completes more work in the same time. Sharing by days alone would ignore efficiency, so a worker who is twice as efficient would be underpaid if both are paid equally for the same days.
PYQ Practice — Statement Analysis
1 If two workers work for equal days, their wages follow the ratio of their efficiencies.
Work done is efficiency times equal time.
2 If A takes 12 days and B takes 6 days, B should get less wage than A for equal days.
B is more efficient and gets twice as much.
3 If efficiencies are equal, wages are shared in the ratio of days worked.
Work done is proportional to days.
4 Wages are shared in the ratio of days taken to finish the work alone.
They are shared in the inverse ratio, which is the ratio of efficiencies.