28 RAS Prelims MCQs on irrigation in Rajasthan cover the sources of irrigation, the canals and the major dams. The Indira Gandhi Canal, the Gang Canal, the Mahi Bajaj Sagar Project and the dams on the Chambal are asked with their lengths, locations and sharing arrangements, and the explanations give the reason for artificial irrigation.

Practice questions based on the RPSC RAS Prelims syllabus. They follow the exam pattern but are not past-paper questions.

Clear filters

Showing 11–20 of 28 questions

RAS Prelims Rajasthan Geography · Irrigation in Rajasthan
Q11. Which river system provides the continuous water supply required for the Indira Gandhi Canal?
RAS Prelims Rajasthan Geography · Irrigation in Rajasthan
Q12. Match List I with List II and select the correct answer using the codes given below:
Old Name of IGNP Lift CanalNew Name
A. Bikaner-Lunkaransar Lift Canali. Dr. Karni Singh Lift Canal
B. Gajner Lift Canalii. Panna Lal Barupal Lift Canal
C. Kolayat Lift Canaliii. Kanwar Sen Lift Canal
D. Phalodi Lift Canaliv. Guru Jambheshwar Lift Canal
RAS Prelims Rajasthan Geography · Irrigation in Rajasthan
Q13. Consider the following districts of Rajasthan:
I. Bikaner
II. Jaisalmer
III. Churu
IV. Hanumangarh
V. Udaipur
Which of the above districts benefit directly from the Indira Gandhi Canal Project network?
RAS Prelims Rajasthan Geography · Irrigation in Rajasthan
Q14. Which of the following is considered the longest lift canal of the Indira Gandhi Canal Project?
RAS Prelims Rajasthan Geography · Irrigation in Rajasthan
Q15. The last operational point of the Indira Gandhi Canal is situated at:
RAS Prelims Rajasthan Geography · Irrigation in Rajasthan
Q16. Select the correct sequence of the Indira Gandhi Canal lift canals geographically from North to South:
RAS Prelims Rajasthan Geography · Irrigation in Rajasthan
Q17. Which of the following is recognized as the oldest modern canal system in Rajasthan?
RAS Prelims Rajasthan Geography · Irrigation in Rajasthan
Q18. The construction of the Gang Canal was completed under the visionary leadership of Maharaja Ganga Singh in the year:
RAS Prelims Rajasthan Geography · Irrigation in Rajasthan
Q19. From which location does the Gang Canal originate before bringing water to the Sri Ganganagar district?
RAS Prelims Rajasthan Geography · Irrigation in Rajasthan
Q20. What was the most significant socio-economic effect of the Gang Canal on the Bikaner princely state?

Answer key for these questions

QCorrect answer
11(b) Satluj and Beas
12(b) A-iii, B-ii, C-i, D-iv
13(a) I, II, III and IV
14(b) Kanwar Sen Lift Canal
15(b) Gadra Road
16(a) Chaudhary Kumbharam - Kanwar Sen - Panna Lal Barupal - Dr. Karni Singh
17(c) Gang Canal
18(b) 1927
19(c) Husainiwala on the Satluj river
20(b) It transformed the dry, arid region into a major grain-producing hub.

Key facts from Irrigation in Rajasthan

  • Rajasthan depends on artificial irrigation because of low and erratic rainfall; wells and tube wells give the highest share of irrigated area.
  • The Indira Gandhi Feeder Canal is 204 km long up to its entry into Rajasthan; the last operational point of the canal is at Gadra Road.
  • The Gang Canal, the oldest modern canal system of Rajasthan, starts at Husainiwala on the Sutlej and was completed in 1927 under Maharaja Ganga Singh.
  • The Mahi Bajaj Sagar dam is in Banswara; Rajasthan and Gujarat share its costs and water in the ratio 45:55.
  • The Chambal dams from downstream to upstream are Kota Barrage, Jawahar Sagar, Rana Pratap Sagar and Gandhi Sagar.
  • Dungarpur is outside the Indira Gandhi Canal command area.

Frequently asked questions

How many RAS Prelims practice MCQs are there on Irrigation in Rajasthan?

This page has 28 practice MCQs on Irrigation in Rajasthan (Rajasthan Geography). Each has the correct answer, and most have an explanation.

Which is the oldest modern canal system of Rajasthan?

The Gang Canal, built under Maharaja Ganga Singh of Bikaner and completed in 1927. It begins at Husainiwala on the Sutlej and brought water to the Sri Ganganagar area.

Where does the Indira Gandhi Canal end?

At Gadra Road in Barmer district, which is the last operational point of the canal. The canal is the longest in India and brings Himalayan water to the Thar desert.

How is the Mahi Bajaj Sagar Project shared?

Rajasthan and Gujarat share the project in the ratio 45:55 for the cost and the water. The dam is on the Mahi river in Banswara district, and the hydroelectricity is allocated under the agreement between the two States.